Site Preparation for Helical Pier Installation
Once the exact locations are determined for the placement of the helical piers, the LRE team begins excavating the necessary amount of soil to prepare for the installation.
Pre-installation Placement of Helical Piers
The helical piers are placed in position in preparation to be driven down into the soil below the foundation.
Installation of Helical Piers
Specialized equipment is used to mechanically drive the helical piers into the ground below the foundation until stronger soil capacities are reached.
Complete Installation of Helical Piers
The helical piers have been successfully installed under the foundation support columns, providing the permanent stabilization needed.
Cleanup of Installation Site
After the installation of the helical pier system, the LRE team backfills the excavated soil and conceals the helical piers to ensure a seamless appearance.